| PROJECT NAME: SAMPLE PROJECT | ||
| PROJECT ADDRESS: 101 MAIN STREET, ANYTOWN, USA | ||
| PERMIT NUMBER: | ||
| COST CODES & BUILDING CATEGORIES | BUDGET | DESCRIPTION OF WORK |
| Project Totals (not including contract change orders) see below | $5,100.000 | enter a brief decription for each category |
| 10000 | REAL ESTATE & START-UP | $100.00 | |
| 11000 | PERMITS & INSPECTIONS | $100.00 | |
| 12000 | ARCHITECTURE / DESIGN / ENGINEERING / SURVEYING | $100.00 | |
| 13000 | SITE-WORK & GRADING | $100.00 | |
| 14000 | DEMOLITION – SALVAGE - ABATEMENT | $100.00 | |
| 15000 | UTILITIES | $100.00 | |
| 16000 | FOOTINGS | $100.00 | |
| 17000 | FOUNDATION & MASONRY | $100.00 | |
| 18000 | WATERPROOFING | $100.00 | |
| 19000 | TERMITE & INSECT (PEST CONTROL) | $100.00 | |
| 20000 | CONCRETE SLABS (HOUSE & GARAGE) | $100.00 | |
| 21000 | STRUCTURAL & ORNAMENTAL STEEL | $100.00 | |
| 22000 | FRAMING & CARPENTRY | $100.00 | |
| 23000 | ROOFING | $100.00 | |
| 24000 | PLUMBING | $100.00 | |
| 25000 | HEATING – COOLING - VENTILATION | $100.00 | |
| 26000 | ELECTRICAL & LIGHTING | $100.00 | |
| 27000 | FIREPLACE & HEARTH | $100.00 | |
| 28000 | INSULATION | $100.00 | |
| 29000 | SIDING & EXTERIOR FINISHES | $100.00 | |
| 30000 | EXT. DOORS - LOCKS - HARDWARE | $100.00 | |
| 31000 | WINDOWS | $100.00 | |
| 32000 | ARCHITRAVE & ENTABLATURE | $100.00 | |
| 33000 | DRYWALL & PLASTER | $100.00 | |
| 34000 | GARAGE DOOR | $100.00 | |
| 35000 | PORCH & DECK | $100.00 | |
| 36000 | INT. DOORS - LOCKS - HARDWARE | $100.00 | |
| 37000 | INTERIOR TRIM & MILLWORK | $100.00 | |
| 38000 | STAIRS & RAILINGS | $100.00 | |
| 39000 | PAINTING | $100.00 | |
| 40000 | DECORATIVE HARDWARE | $100.00 | |
| 41000 | GUTTERS & DOWNSPOUTS | $100.00 | |
| 42000 | CABINETS & BUILT-INS | $100.00 | |
| 43000 | COUNTERTOPS | $100.00 | |
| 44000 | FLOORING | $100.00 | |
| 45000 | TILE & STONE | $100.00 | |
| 46000 | MIRRORS & MEDICINE CABINETS | $100.00 | |
| 47000 | CLOSETS - WARDROBES - STORAGE | $100.00 | |
| 48000 | SHOWER GLASS & ENCLOSURES | $100.00 | |
| 49000 | WALL & CEILING FINISHES | $100.00 | |
| 50000 | CLEANING & WASTE MANAGEMENT | $100.00 | |
| 51000 | LANDSCAPING & HARDSCAPING | $100.00 | |
| 52000 | DRIVEWAY & SIDEWALKS | $100.00 | |
| 53000 | APPLIANCES | $100.00 | |
| 54000 | TEMPORARY FACILITIES | $100.00 | |
| 55000 | TOOLS & EQUIPMENT | $100.00 | |
| 56000 | MAINTENANCE – REPAIR - WARRANTY | $100.00 | |
| 57000 | SAFETY & SURFACE PROTECTION | $100.00 | |
| 58000 | HOME AUTOMATION & SECURITY | $100.00 | |
| 59000 | PROJECT MANAGEMENT & GENERAL ADMINISTRATION | $100.00 | |
| 60000 | FURNITURE | $100.00 | |
| CONTRACT CHANGE ORDER #1 | $100.00 | |
| CONTRACT CHANGE ORDER #2 | $100.00 | |
| CONTRACT CHANGE ORDER #3 | $100.00 | |
| CONTRACT CHANGE ORDER #4 | $100.00 | |
| CONTRACT CHANGE ORDER #5 | $100.00 | |
| CONTRACT CHANGE ORDER #6 | $100.00 | |
| CONTRACT CHANGE ORDER #7 | $100.00 | |
| CONTRACT CHANGE ORDER #8 | $100.00 | |
| CONTRACT CHANGE ORDER #9 | $100.00 | |
| CONTRACT CHANGE ORDER #10 | $100.00 | |
| PROJECT TOTALS (INCLUDING CCO'S) | $6,100.00 |